Planning and Project Control - Construction of emerald unit of Bitumen Shiraz - Preparation and commissioning of the third tower of Shiraz factory
  • Planning and Project Control - Construction of emerald unit of Bitumen Shiraz - Preparation and commissioning of the third tower of Shiraz factory
  • Planning and Project Control - Construction of emerald unit of Bitumen Shiraz - Preparation and commissioning of the third tower of Shiraz factory
  • Planning and Project Control - Construction of emerald unit of Bitumen Shiraz - Preparation and commissioning of the third tower of Shiraz factory

Planning and Project Control - Construction of emerald unit of Bitumen Shiraz - Preparation and commissioning of the third tower of Shiraz factory

Type of file: MSP-EXCEL-PDF | Date: Gregorian - Shamsi| Gantt Chart - Critical-Updated Schedule-Project Control-Schedule-Report -Monthly and Weekly Reporet | Duration: 210,132| Activity Number: 1002,343| Language: English | Range of Date: 2008

Supplier information

Kabiri Co. (Learning Project Management, Planning and Project Control, Computer and Laptop Sales and Repair)

Iran (Islamic Republic of), Tehran

Manufacturer, Retailer, Service provider

Planning, Project Control, Delayed Delivery, Learning Project Management, Learning Planning, Learning Project Control, Schedule Consultation, Computer repair, computer Services, Computer sales, Laptop sales, Computer help, Construction scheduling schedule, Recruitment, Planning with msp, Planning and control of construction projects

View supplier website

Specifications

Made in
Iran
Type of file
MSP-EXCEL-PDF
Date
Gregorian - Shamsi
The chart
Gantt chart
Critical Path
Yes
Updated Schedule
Yes
Schedule
Yes
Project Control
Yes
Report
Monthly - Weekly
Duration
210,132
Activity Number
1002,343
Language
English
Range of Date
2008
Price
19 $

Product description

1. Detailed Scheduling
2. Critical path
3. Schedule updated
4. Project control
5. Monthly report
6. Weekly report
7. Schedule with Gantt Charts Chart, Critical Path, Breakdown Structure, Preconditions Relationship Includes Main Activities:

BITUMEN EMULSION

   CIVIL WORKS

      DESTROY& TRANSITION CONCRETE LAYER

      CONCRETE WORK

         EQUIPMENT FOUNDATION

            SH-2TK-3001 A

            SH-2TK-3001 B

            SH-2TK-3001 C

            SH-2TK-3001 D

            SH-2TK-3001 E

            SH-2TK-3001 F

            SH-2TK-3002

            SH-2TK-3003

            SH-2TK-3004

            SH-2V-3001

            SFC 20

            SH-2E-3001

            SH-2P-3001 A

            SH-2P-3001 B

            SH-2P-3002 A

            SH-2P-3002 B

            SH-2P-3003 A

            SH-2P-3003 B

            SH-2P-3004 A

            SH-2P-3004 B

            SH-2P-3005 A

            SH-2P-3005 B

            Emulsion Unit

         CONCRETE STRUCTURE

            PIPE RACK FOUNDATION

               P.R. 01

               P.R. 02

               Pipe Rack

            TRENCHES

            SLEEPER & PIPE SUPPORT

            Access Platform

            LIGHTING POLE

      PAVING & FINAL SITE LEVELING & DITH(EDGE)

   A/G PIPING

      CARBON STEEL PIPE & VALVE & FITTING

         CARBON STEEL PIPE ≤ 2"

            Installation

         CARBON STEEL PIPE > 2"

            Prefabricate

            Installation

         THREAD FITTINGS

         STEAM TRACING

         STEAM TRAPS & STRAINER & FLANGES

         VALVE

      SUPPORTS

         CARBON STEEL PIPE ≤ 2" SUPPORT

         CARBON STEEL PIPE > 2" SUPPORT

   MECHANICAL EQUIPMENT

      STATIC

         TOWERS

            SH-2PK-3001

         EXCHANGERS

            SH-2E-3001

         TANKS & VESSELS

            SH-2TK-3001 A

               BOTTOM

                  ANNULAR PLATES & BACKING STRIPES

                  BOTTOM PLATES

               SHELL PLATES

                  INSTALLATION INCLUDING FIT UP